在沼氣塔的使用過程中,我們所期望的就是它可以發(fā)揮廢氣處理效果,達(dá)到環(huán)評(píng)要求,所以這就要求我們?cè)谠O(shè)備的使用過程中能夠正確操作,并做好日常保養(yǎng)工作,但是沼氣塔經(jīng)過長時(shí)間的使用,很容易在內(nèi)部積累一些頑垢,十分影響脫硫塔的性能!今天沼氣生物脫硫的小編就來為大家介紹一下脫硫塔結(jié)垢如何清洗。
In the process of using biogas tower, what we expect is that it can give full play to the effect of waste gas treatment and meet the requirements of environmental impact assessment. So this requires us to operate correctly in the process of using equipment and do well in daily maintenance. But after a long time of using biogas tower, it is easy to accumulate some intractable fouling inside. It greatly affects the performance of desulfurization tower! Today, biogas desulfurization Xiaobian will introduce you how to clean the scale of desulfurization tower.
1. 清洗脫硫塔底部垢
1. Cleaning the bottom scale of desulfurization tower
首先針對(duì)脫硫塔底部的污垢進(jìn)行清洗!將清洗劑加入到底部的循環(huán)液中,利用脫硫塔底部的循環(huán)泵循環(huán)清洗,使塔底的污垢清洗干凈,保證脫硫塔疏水管底部不被埋在垢層中!脫硫塔底部垢的清洗采用三步。
Firstly, the fouling at the bottom of the desulfurization tower is cleaned. The cleaning agent is added to the circulating liquid at the bottom of the desulfurization tower, and the circulating pump at the bottom of the desulfurization tower is used to clean the fouling at the bottom of the tower, so as to ensure that the bottom of the drain pipe of the desulfurization tower is not buried in the fouling layer. Three steps are used to clean the fouling at the bottom of the desulfurization tower.
2. 旋分器管底部疏水管的清洗疏通
2. Cleaning and dredging of drain pipe at bottom of cyclone pipe
脫硫塔底部的污垢清洗完成后,再進(jìn)行旋分器管底部疏水管的清洗疏通工作!首先在RS2 的壓力下打開人孔,在系統(tǒng)所有設(shè)備不停車的狀態(tài)下,充分利用機(jī)器人自動(dòng)清洗技術(shù),控制爬行機(jī)構(gòu)(確保執(zhí)行每只旋分器管的清洗工作),牽引柔性聚氯乙烯噴淋管行進(jìn),圍繞脫硫塔一圈,使清洗機(jī)構(gòu)對(duì)應(yīng)脫硫塔的每只旋分器管,噴灑位置要準(zhǔn)確,定時(shí)進(jìn)行噴灑清洗劑,持續(xù)進(jìn)行,檢測觀察清洗效果和其他可能出現(xiàn)的情況!
After cleaning the dirt at the bottom of the desulfurization tower, the cleaning and dredging work of the drain pipe at the bottom of the cyclone pipe is carried out. Firstly, the manhole is opened under the pressure of RS2, and the crawling mechanism is controlled by fully utilizing the automatic cleaning technology of the robot under the condition that all the equipment in the system does not stop. The flexible polyvinyl chloride spraying pipe is introduced to move around the desulfurization tower, so that the cleaning mechanism corresponds to each cyclone pipe of the desulfurization tower. The spraying position should be accurate, the cleaning agent should be sprayed regularly and continuously, and the cleaning effect and other possible situations should be monitored and observed.
好了,今天的精彩內(nèi)容就先給大家介紹到這里了,歡迎大家收藏我們的網(wǎng)站:http://ttzdb.com,我們將會(huì)定期更新更多的精彩內(nèi)容!大家搜索關(guān)鍵詞:生物脫硫,這樣也可以找到我們!謝謝大家的支持!
Well, today's wonderful content will be introduced to you first. Welcome to collect our website: http://ttzdb.com, we will update more wonderful content regularly! We search for key words: biological desulfurization, so we can also find! Thank you for your support!